Cash flow is the lifeblood of construction. Adjudication is the usual route for resolving payment disputes quickly, keeping money moving while the parties argue about the final answer.
What Is Construction Adjudication and How Does It Work?
Under the Housing Grants, Construction and Regeneration Act 1996 (HGCRA), as amended by the Local Democracy, Economic Development and Construction Act 2009, a party to a qualifying construction contract may refer a dispute to adjudication “at any time”. That right cannot be contracted out of, and the rapid decision binds on an interim basis.
Why Is Adjudication So Popular in Construction Disputes?
The benefits are speed and cash-flow protection (pay now, argue later”), a specialist decision-maker, procedural flexibility, robust TCC enforcement and tactical leverage in the final account.
The limitations: a compressed timetable for respondents, each side usually bearing its own costs, and a decision that remains open to final determination.

Why Clear Payment Demands, Applications and Notices Matter in Adjudication
If a valid payment application sets the “notified sum” and the payer serves no valid payment notice or pay less notice in time, the payer must ordinarily pay it, even if that exceeds the true value of the work.
This payment-notice route enforces the statutory payment bargain rather than determining true value. This is sometimes referred to as the “smash and grab” process associated with adjudication.
However, a general demand letter is not automatically a payment application, payment notice or pay less notice, so clarity matters. Those seeking payment need to be careful to be clear what document they have sent, and to be clear in accordance with HGCRA when payments are due. Equally, those from whom payment is requested should take care not to ignore something that could later be held as a payment application.

What Should a Clear Payment Demand Contain?
- Details of the contract, and the payment cycle or decision relied on.
- Principal sum, VAT and interest.
- Due and final dates for payment.
- Credits received and the balance payable.
- Any specific compliance deadline.
In addition to the above under the statutory scheme, contracts may also have further requirements, and should be checked carefully.
Conclusion: Adjudication Rewards the Party That Has Done Its Homework
Adjudication rewards the party that has done its homework. Taking each step in the payment machinery clearly, validly and on time is far cheaper than repairing it once a dispute has begun.
Need help with a payment dispute or an adjudication? Contact the Commercial Litigation team at Fiona Bruce Solicitors LLP on 01925 263 273 or at legal@fionabruce.co.uk.
The contents of this post do not constitute legal advice and are provided for general information purposes only ■